Harbour Gate, Portsmouth - Bill of Quantities
P2024-004 - Berkeley Group - Mixed-Use Development
7
SECTIONS
18
ITEMS
Ref
Description
Unit
Qty
Rate
Value
1.0
Preliminaries
£387,500.00
1.1
Site SetupHoarding, signage, temporary services, access roads
Item
1
£125,000.00
£125,000.00
1.2
Welfare FacilitiesCanteen, drying room, toilets, offices
Wk
78
£1,750.00
£136,500.00
1.3
Site ManagementSite manager, project manager, general attendance
Wk
78
£1,615.38
£126,000.00
2.0
Groundworks
£1,842,000.00
2.1
ExcavationBulk dig, reduced level excavation, disposal
m³
8,400
£85.00
£714,000.00
2.2
FoundationsStrip footings, pad foundations, reinforcement
m³
2,200
£340.00
£748,000.00
2.3
DrainageFoul and surface water drainage, manholes, connections
m
1,520
£250.00
£380,000.00
3.0
Substructure
£1,098,000.00
3.1
Ground Floor SlabInsulation, DPM, reinforced concrete slab, power float finish
m²
4,200
£165.00
£693,000.00
3.2
Below DPC WallsEngineering brickwork, blockwork, cavity insulation, DPC
m²
1,800
£225.00
£405,000.00
4.0
Superstructure
£4,127,000.00
4.1
External WallsFacing brickwork, cavity wall construction, insulation, ties
m²
6,800
£195.00
£1,326,000.00
4.2
Internal WallsBlockwork partitions, metal stud partitions, plasterboard
m²
5,200
£125.00
£650,000.00
4.3
Upper FloorsPrecast concrete planks, structural topping, edge beams
m²
4,200
£285.00
£1,197,000.00
4.4
Roof StructureTimber trusses, flat roof decking, insulation, membrane
m²
3,400
£280.00
£954,000.00
5.0
Building FabricWindows, doors, ironmongery, plastering, decorating, flooring
Item
1
£2,180,000.00
£2,180,000.00
6.0
Mechanical & ElectricalHVAC, electrical installation, plumbing, fire alarm, data
Item
1
£1,950,000.00
£1,950,000.00
7.0
External WorksLandscaping, car parking, boundary treatments, drainage
Item
1
£815,500.00
£815,500.00