Daily Logs

GT

Weather Conditions

Temperature 9°C
Wind 12 mph SW
Rain Light showers AM

Workforce on Site

Total: 34 operatives

TradeCompanyHeadcountHours
Site ManagementDirect207:00 - 17:00
GroundworkersHampshire Groundworks607:30 - 16:30
BricklayersItchen Valley Brickwork407:30 - 16:30
CarpentersDirect307:30 - 16:30
Steel FixersWessex Steelwork407:00 - 15:30
ElectriciansSolent Electrical308:00 - 17:00
PlumbersNew Forest Plumbing208:00 - 16:30
ScaffoldersChandler Scaffolding407:00 - 15:30
LabourersDirect607:30 - 16:30

Plant on Site

8T Tracked Excavator (PLT-001) In Use
3T Swivel Dumper (PLT-003) In Use
Telehandler JCB 535-95 (PLT-010) Idle
Concrete Pump (hired - daily) In Use
Tower Crane - Potain MDT 219 In Use

Work Completed Today

Groundworks
Superstructure
M&E First Fix

Visitors Log

NameCompanyPurposeInOut
Mark CollinsTaylor WimpeyClient inspection10:0012:30
Sarah PhillipsHampshire CCBuilding control09:1510:45
David WarrenStructural EngineersFoundation check14:0015:30

Deliveries Received

TimeSupplierMaterialQtyStatus
07:45Hanson AggregatesReady-mix concrete C3018 m³Accepted
09:30JewsonFacing bricks (Ibstock)4 palletsAccepted
11:15British SteelStructural sections8.2 tonnesAccepted
14:00Travis PerkinsDrainage pipes & fittings1 loadPartial

Issues / Delays Noted

Site Photographs

Upload

Previous Logs

Friday 21 Mar 2026
Steel erection Block A. Drainage runs plots 5-7.
32
Complete
Thursday 20 Mar 2026
Foundation pour plots 12-16. Brickwork plots 3-4.
36
Complete
Wednesday 19 Mar 2026
Excavation Block C commenced. Scaffold advance.
30
Complete
Tuesday 18 Mar 2026
Rain delay AM. Reduced programme afternoon only.
18
Weather
Monday 17 Mar 2026
Piling rig mobilised. Site compound relocated.
28
Complete
Friday 14 Mar 2026
Concrete pour Block B slab. M&E coordination meeting.
35
Complete
Thursday 13 Mar 2026
Drainage connections. External wall brickwork ongoing.
33
Complete