Oakfield Manor Phase 2 - Programme

Contract period: Sep 2025 - Sep 2026 (56 weeks)
72%
COMPLETE
+2 wk
AHEAD
28
WKS LEFT
Task / Phase
1. Mobilisation2 wks
Site setup & hoarding1 wk
Welfare & services1 wk
2. Groundworks4 wks
Bulk excavation2 wks
Drainage & services2 wks
3. Foundations3 wks
Strip foundations2 wks
Ground floor slab1 wk
4. Substructure4 wks
Blockwork to DPC3 wks
Damp proof course1 wk
5. Frame6 wks
Timber frame erection4 wks
Roof structure2 wks
6. Envelope5 wks
External brickwork3 wks
Windows & doors2 wks
7. M&E First Fix4 wks
8. Plastering3 wks
9. M&E Second Fix3 wks
10. Joinery3 wks
11. Decoration3 wks
12. External Works4 wks
13. Snagging2 wks
14. Handover1 wk
Practical CompletionMilestone
February 2026
March 2026
April 2026
May 2026
June 2026
Frame (4/6 wks)
Timber frame
Roof
Envelope (5 wks)
Brickwork
Windows
M&E 1st Fix (4 wks)
Plastering (3 wks)
M&E 2nd Fix (3 wks)
Joinery (3 wks)
Decoration (3 wks)
External Works (4 wks)
Snagging (2 wks)
Handover